Campus construction update: Emergency Services Expansion – May 3, 2024

May 3, 2024




CONSTRUCTION UPDATE

On May 1, construction crews covered the windows behind the east side exterior canopy with plywood, in order to protect the glass from any potential airborne debris during the demolition of the canopy and octagon.

Starting today, May 3, construction crews will extend their laydown area in the ANMC hospital east side parking lot, including part of the existing roadway. Traffic will be rerouted and signage will be placed to direct the flow of traffic. If you are visiting this area, please be alert of ongoing construction activities and new traffic patterns. Please see the graphic below for a visual of the impacted area.

PARKING UPDATE

Starting on Friday, May 3, construction crews will take over more of the ANMC hospital east side parking lot for construction staging. The east lot parking is reserved for patients. Additional parking locations include: the ANMC Patient Housing Parking Garage (north of the hospital), the Denali Parking Garage (east of the hospital), the Flattop Mountain Parking Garage (south of the hospital).


Browse More Stories


Share This Story